For the construction of this infrastructure, 312.04 metres of corrugated high-density polyethylene pipe with a 12-inch diameter were installed. Additionally, nine inspection wells were built to facilitate network inspection and maintenance, and 12 sanitary discharges were enabled to connect homes to the main pipe.
The work registers an indirect benefit for 1,783 residents of the locality. As part of the works and within the framework of transparency and accountability, an information board was placed detailing the progress. The municipal president highlighted that having basic services translates into development for the municipality.
“"We are delivering more than infrastructure; having basic services translates into well-being and development, this is the progress we want for our municipality"